Road Work Update
Published: November 28, 2016
During the rainy weekend, on Thursday morning, crews responded to a fallen tree on Bei Road in Guerneville, and on Saturday night, to a light pole down on Regional Parkway and a rock slide on Porter Creek Road.
Paving and Pavement Preparations
- All paving and road construction for the summer paving program is complete. Remaining work includes shoulder backing, guard rail construction, raising utility covers, survey monument construction, and striping.
Road Maintenance Projects
- Road maintenance crews will be working Monday through Thursday patching potholes and doing roadside mowing in various locations around Sonoma County.
- The Bridge crew is repairing guardrails on various locations.
- The Culvert and Guerneville crews are cleaning culverts at various locations and installing culverts on Trinity Road.
- The Traffic crew is repairing signs at many locations and helping road crews as needed.
Construction Projects
- Highway 12 Improvements, between Agua Caliente Road to Boyes Boulevard: final construction activities
- Construction of the Healdsburg Intermodal Facility: final construction activities
- Intersection Improvements at Adobe Road and East Washington Street: traffic signal construction, and striping layout and installation
Plan your Commute
Please be prepared for single lane traffic control and minor delays during active road work, and drive safely in construction zones. The shoulder will be closed on Adobe Road and East Washington Street.