During the weekend storms, crews responded to rocks on the road on Stewarts Point Skaggs Springs Road, flooding on Mark West Station Road at Starr Road, and a fallen tree blocking Pleasant Hill Road.
Paving and Pavement Preparations
- All paving and road construction for the summer paving program is complete. Remaining work includes shoulder backing, guard rail construction, raising utility covers, survey monument construction, and striping.
Road Maintenance Projects
- Road maintenance crews will be working Monday through Thursday patching potholes and doing roadside mowing in various locations around Sonoma County.
- The Bridge crew is repairing guardrails on various locations.
- The Culvert and Healdsburg crews are cleaning culverts at various locations.
- The Traffic crew is repairing signs at many locations and helping road crews as needed.
Construction Projects
- Highway 12 Improvements, between Agua Caliente Road to Boyes Boulevard: final construction activities
- Construction of the Healdsburg Intermodal Facility: final construction activities
- Intersection Improvements at Adobe Road and East Washington Street: traffic signal construction, and striping layout and installation
Plan your Commute
Please be prepared for single lane traffic control and minor delays during active road work, and drive safely in construction zones. The shoulder will be closed on Adobe Road and East Washington Street.