June 29, 2017 | Sonoma Public Infrastructure

2017 Paving ProgramMoves Forward

On June 6th, the Sonoma County Board of Supervisors approved the first contracts of the 2017 Pavement Program, kicking off construction on 54.49 miles of roads this summer, as part of a 97 mile program approved by the Board last year. The remaining 42.51 miles are slated for construction in 2018. When the entire 2017 program is completed the County will have paved approximately 300 miles since the summer of 2013, funded with over $65 Million in General Fund Contributions from the Board of Supervisors. Read full story


June 27, 2017 | Human Resources Department

17th Annual Day of Caring Event

County of Sonoma and City of Santa Rosa employees will join forces on Wednesday, September 13, 2017, for the 17th annual Day of Caring event! Employees will participate in a day of service, working on a variety of projects ranging from painting, gardening, park trail work, packaging items at a food bank, graffiti removal and more. We are currently accepting projects from non-profit partners of the County and City Read full story


June 27, 2017 | Sonoma Public Infrastructure

Road Work Update

This week’s current road work includes pothole, sign, and guardrail repair, resurfacing, vegetation removal, clearing debris, installing culverts, retaining wall construction, striping and stenciling. Hauser Bridge Replacement activities continue. Read full story


June 12, 2017 | Department of Health Services

Tobacco Retail License Renewal

By June 30, 2017, all licensed tobacco retailers located in the unincorporated areas of Sonoma County must renew their Tobacco Retail License from the Sonoma County Health Department in order to continue selling tobacco products (including electronic cigarettes). Read full story


June 07, 2017 | Board of Supervisors Department

2017 Paving Program Moves Forward Despite Storm Damage

Today, the Sonoma CountyBoard of Supervisors approved the first contracts of the 2017 Pavement Program, kicking off construction on 54.49 miles of roadsthis summer, as part of a 97 mile program approved by the Board last year. Read full story


June 05, 2017 | Sonoma Public Infrastructure

Road Work Update

We are potholing; clearing storm debris; trimming brush; stenciling; andrepairing culverts, signs, a truss, and a guardrail. We’re also repairing Austin Creek Roadand working on Hauser BridgeReplacement. Read full story


May 22, 2017 | Sonoma Public Infrastructure

Road Work Update

We're continuing repairs on HotSprings Road. Crews are potholing, clearing storm debris, trimming brush,preparing Vacation Beach Summer Crossing, stenciling, fixing culverts andsigns. Construction activities for the Hauser Bridge Replacement are underway. Read full story


May 16, 2017 | Human Resources Department

Sun Safety Is Not Just For Vacation

The warm sun may feel good on your skin but the sun’s rays can cause wrinkles, age spots and skin cancer.  In fact, most skin cancers are related to sun exposure. Protect your skin and help prevent damage by using sunscreen throughout the year. Read full story


May 16, 2017 | Sonoma Public Infrastructure

Construction Starts on Hauser Bridge Replacement

This week, construction ramped up on the replacement of Hauser Bridge, located on Hauser Bridge Road over the South Fork of the Gualala River about 4 miles east of the junction of Highway 1 and Kruse Ranch Road, near Cazadero. Read full story


May 16, 2017 | Sonoma Public Infrastructure

Road Work Update

Crews are potholing, trimming brush, preparing bridge decks at Odd Fellows' summer crossing, resurfacing, stenciling, repairing culverts and signs. Repairs on Hot Springs Road will begin later this week and the road is expected to open in early June. Construction activities for the Hauser Bridge Replacement are underway. Read full story